Item | Comment | |
---|---|---|
done |
Scribe Molding |
install on cabinet baseboards |
done |
ceiling in electric room |
fix hole made for fridge water |
done |
kitchen walls |
finish various spots in progress (esp. under cabinets) |
done |
drawer face screw holes |
redrill for drawers either side of stove |
done | knobs and pulls |
install remaining pulls |
done |
cabinet door |
reset left of microwave (rubs when opening) |
done |
cabinet doors |
fix various rattles and loose screws |
done |
all appliances |
show Ray how to safely move out and back in |
done |
drawers |
check closing mechanisms (esp. right of stove) |
done |
set stove even (lower front) |
stove raised before drawers were lowered |
Howard's Kitchen Studio - Per Plan
Item | Comment | |
---|---|---|
done |
Counter Top Seam |
correct white edges on large part of seam |
done |
Counter Splash Seams |
clean excess adhesive on sides and top of splashes |
done |
Counter Underside |
clean excess adhesive on all counters |
done |
Soap Dispenser |
provide missing part (tube) |
done |
Sink Faucet Head |
correct difficulty pulling and replacing |
done |
Freezer |
correct snapping sound when door is opened |
Additional Work
Item | Comment | |
---|---|---|
done |
light switches |
swap switches by outside door |
done |
under-cabinet lights |
move to avoid accidental contact |
done |
phone hookup |
move lower and away from back wall |
done |
windows |
caulk sills, replace miniblind fixtures |
done |
wall cabinet by sink and outside door |
explore options for better access |
New Pictures.....
Bakers Rack
Oven Door Catastrophe! (fixed 2 weeks later).